Sequoyah
Hills Wastewater Rehabilitation Phase 1 – Manhole repair work requiring the closure of the eastbound inside
lane of Kingston Pike between Lyons View Pike and Kingston Park Drive daily
from 9 a.m. – 3 p.m. is scheduled for Wednesday, March 13, and Thursday, March
14. One eastbound lane and both westbound lanes will be maintained while this
work is completed. Access to businesses and driveways will also be maintained.
Sequoyah
Hills Wastewater Rehabilitation Phase 2 – Construction activity scheduled to begin
this week on Cherokee Boulevard has been postponed until further notice. Morgan
Construction will continue with scheduled work on Keowee Avenue (between
Southgate Road and West Nokomis Circle) and Taliluna Avenue (between Tugaloo
Drive and Kenesaw Avenue). Work in these areas will require daily road
closures between 7 a.m. – 5 p.m.