March 22, 2019 Update – Painter Avenue Closure
Extended Through Mid-April –
Excavation work at the intersection of Painter Avenue and Concord Street has
been extended through mid-April. Intermittent lane shifts will be implemented
on Concord Street as needed next week in association with manhole replacement
work. Two-way traffic will be maintained at all times on Concord Street.
Painter Avenue will remain closed to vehicle traffic through the end of March.
Alternate routes around the closure zone will include Jersey Avenue, Lindsay
Place, and Sullins Street.
Following
completion of work on Painter Avenue, a closure of the Third Creek Greenway
lasting approximately one week will be required between the west entrance/exit
to Tyson Park and the trail split near Safety City. A detour will be set up via
Painter Avenue while this section of greenway is closed. All traffic and
greenway impacts will be communicated by KUB and the contractor via onsite
signage, media advisories, and on social media platforms. Construction
affecting Painter Avenue and the Third Creek Greenway will not be performed at
the same time, and related closures will not occur during the same period. See map.