June 7, 2019 Update –
Contractor East
Tennessee Pipeline crews continued ‘potholing’ work to locate the presence and
depth of existing underground utilities on East Sunset Drive this past week.
Crews also began boring in sections of natural gas pipeline on East Sunset
Drive this week. The boring crew will work between the 5200 and 5600 blocks on
East Sunset Drive next week.
Boring rig set up in the utility easement on East Sunset Drive.