Sequoyah Hills Wastewater Rehabilitation – Construction crews will
work in the following areas next week with intermittent daily road closures
between 7 a.m. – 5 p.m.:
·
Cedarhill Road between
Scenic Drive and Whitlow Avenue (intermittent road closures as needed for
paving and restoration)
·
Kenesaw Avenue between
Woodland Drive and Iskagna Drive (intermittent road
closures as needed for paving and restoration)
·
Keowee Avenue between
Kenesaw Avenue and Talahi Drive
Crews will also work on the following roads with intermittent lane
closures between 7 a.m. – 5 p.m.:
·
Cherokee Boulevard
between Kenesaw Avenue and Southgate Road (westbound lane closed during daytime
work hours with traffic flow detoured via Kenesaw Road, Taliluna Avenue, and
Southgate Road)
-
Eastbound traffic flow
on this stretch of Cherokee Boulevard and Sequoyah Greenway will remain open at
all times
·
Kenesaw Avenue between
Talahi Drive and Keowee Avenue
Crews will also work in the following off-road easements with no
traffic impacts:
·
Back property between
Holloway Drive and Whitlow Avenue (restoration)
·
Easement between
Scenic Drive and Holloway Drive (wastewater rehabilitation and restoration)
·
Easement between
Holloway Drive and Whitlow Avenue (Wastewater rehabilitation and restoration)
Concrete Restoration – This work has been delayed as the concrete subcontractor
completes work in other areas. This work will be performed based on contractor
availability. Once started, this work will require 24-hour road closures.
The 24-hour time frame includes crews setting up forms, pouring and finishing
concrete, time for concrete to cure overnight, and removal of forms the
following day. Access to driveways will be maintained. Work on these roads will
be scheduled so that all roads are not closed at the same time:
·
Windgate Street between
Oakhurst Drive and Iskagna Drive
·
Iskagna Drive between
Kenesaw Avenue and Woodside Street
·
Kenesaw Avenue between
Talahi Drive and Iskagna Drive (This will require a lane closure due to the
repair site being on one side of the road)
· Talahi Drive between
Kenesaw Avenue and Keowee Avenue
Vegetation Management – Vegetation work is
complete between Whitlow Avenue and Holloway Drive area.
Closed-circuit Television Inspection – Crews will continue to
work throughout the Phase 2 area next week. Temporary lane closures will be
implemented as needed when crews are present.
Sequoyah Park – Morgan Construction and their subcontractors continue to
rehabilitate the existing wastewater main and manholes in Sequoyah Park. See
the attached map showing current work corridors within the park. The park, all
entrances and parking areas, and boat ramp remain open during this work. Morgan
Construction is also maintaining a fenced area in the middle parking lot for
equipment and materials storage. KUB has coordinated work in the park with City
of Knoxville Parks and Recreation and the Kingston Pike Sequoyah Hills
Association. Informational banners have been placed in the park entrances/parking
areas to provide park visitors with details about the wastewater rehabilitation
work. Updates on the progress of work in the park will be posted weekly and as
needed on this blog site.
Natural Gas System Work – Natural gas work has been temporarily suspended
in Sequoyah Hills as crews have been shifted to work on another area on the
system.