Holston Hills Natural Gas Project

June 28, 2019 Update – Contractor East Tennessee Pipeline crews continued boring in sections of natural gas pipeline through the 5500-block of East Sunset Drive this past week. The boring crew will continue to progress toward the 5800-block of East Sunset Drive next week. Crews will not work on July 4