September 13,
2019 Update –Contractor
East Tennessee Pipeline crews will directional bore to install new natural gas
main from the 5500 block east to the 5800 block on Holston Hills Road. Crews
will also bore across Holston Hills Road at Cliffside Lane and continue with
installation of 225-feet of main on that street. Customer service line
connections will be made between the 5900 and 5300 blocks on E. Sunset Drive.