September 20, 2019 UPDATE –Construction crews will work in the following areas next week
with intermittent road closures between 7 a.m. – 5 p.m.:
- Agawela
Avenue between Taliluna Avenue and Cherokee Boulevard
- Kenesaw
Avenue between Taliluna Avenue and Cherokee Boulevard
- Bluff View Road between Southgate Road and Holloway Drive
Crews
will also work on the following roads with intermittent lane closures
between 7 a.m. – 5 p.m.
- Taliluna Avenue between Agawela Avenue and Southgate Road
Crews
will also work in the following off-road easements with minimal traffic
impacts:
- Easement between Sequoyah Avenue and Taliluna Avenue
Yard/Easement
Restoration – Weather
has had a major impact on yard/easement restoration efforts as recent hot and
dry weather have combined to prevent planted grass seed from taking root and
growing. KUB’s contractor, Morgan Construction, and their subcontractors will
revisit restoration areas in the coming weeks, once temperatures start to cool
and rain is in the forecast.
Closed-circuit
Television Inspection – Crews will continue to work throughout the Phase 2 area next
week. Temporary lane closures will be implemented as needed when crews are
present.
Sequoyah
Park –
Morgan Construction and their subcontractors continue to rehabilitate the
existing wastewater main and manholes in Sequoyah Park. See the attached map
showing current work corridors within the park. The park, all entrances and
parking areas, and boat ramp remain open during this work. Morgan Construction
is also maintaining a fenced area in the middle parking lot for equipment and
materials storage. KUB has coordinated work in the park with City of Knoxville
Parks and Recreation and the Kingston Pike Sequoyah Hills Association.
Informational banners have been placed in the park entrances/parking areas to
provide park visitors with details about the wastewater rehabilitation work.
Updates on the progress of work in the park will be posted weekly and as needed
on this blog site.
Natural
Gas System Work – Crews have resumed natural gas inspection and maintenance
work at various locations throughout Sequoyah Hills. This work may require
short term traffic impacts in the immediate area where crews are working.
(Sequoyah
Hills) Scenic Drive Road Closure [September 23] – KUB crews will close a short section of
Scenic Drive between Blows Ferry Road and Choctaw Road to through traffic from
8 a.m. – 4 p.m., on Monday, September 23, as work is performed on the
wastewater collection system in the area. Alternate routes include Choctaw Road,
Chickasaw Road, South Garden Road, and Navaho Road. Appropriate signage and
flaggers will be on site to assist with traffic control. Follow-up advisories
will be issued as necessary.