Kingston Pike/Homberg Drive Water Main Project


September 20, 2019Construction began on Kingston Pike this past Sunday, September 15.  Crews are working overnight with TDOT issued work hours from 7 p.m. to 6 a.m., Sunday evening through Friday morning. Construction progressed north across the east bound lanes of Kingston Pike then westward through the center turn lane from the intersection of Homberg Dr and Kingston Pike to the intersection of Westwood Rd. Crews will perform water sample testing over the weekend. Customer service lines, fire hydrants, and connecting to existing water mains will take place in the coming weeks. Paving crews are working to finish road patches on Homberg Drive, as well as repaving recent work areas in Kingston Pike, on a nightly basis as TDOT requirements call for all traffic lanes to reopen by 6 a.m. each morning. The center turn lane will remain closed on this section of Kingston Pike for the duration of the project.