Friday, September 13, 2019

Sequoyah Hills Wastewater Project


September 13, 2019 UPDATE – Construction crews will work in the following areas next week with intermittent road closures between 7 a.m. – 5 p.m.:
·         Agawela Avenue between Taliluna Avenue and Cherokee Boulevard
·         Kenesaw Avenue between Taliluna Avenue and Cherokee Boulevard
·         Bluff View Road between Southgate Road and Holloway Drive

Crews will also work on the following roads with intermittent lane closures between 7 a.m. – 5 p.m.
·         Taliluna Avenue between Agawela Avenue and Southgate Road 

Crews will also work in the following off-road easements with minimal traffic impacts:
·         Easement between Agawela Avenue and Kenesaw Avenue in Sequoyah Village Apartments (Restoration)
·         Easement between Iskagna Drive and Woodland Drive (Restoration)
·         Easement between Sequoyah Avenue and Taliluna Avenue (Restoration)

Closed-circuit Television Inspection – Crews will continue to work throughout the Phase 2 area next week. Temporary lane closures will be implemented as needed when crews are present.

Sequoyah Park – Morgan Construction and their subcontractors continue to rehabilitate the existing wastewater main and manholes in Sequoyah Park. See the attached map showing current work corridors within the park. The park, all entrances and parking areas, and boat ramp remain open during this work. Morgan Construction is also maintaining a fenced area in the middle parking lot for equipment and materials storage. KUB has coordinated work in the park with City of Knoxville Parks and Recreation and the Kingston Pike Sequoyah Hills Association. Informational banners have been placed in the park entrances/parking areas to provide park visitors with details about the wastewater rehabilitation work. Updates on the progress of work in the park will be posted weekly and as needed on this blog site.

Natural Gas System Work – Crews have resumed natural gas inspection and maintenance work at various locations throughout Sequoyah Hills. This work may require short term traffic impacts in the immediate area where crews are working.


(Bearden Area) Kingston Pike Lane Closures [Overnight, September 16 – Mid October] – KUB crews will implement lane closures of both the eastbound and westbound lanes of Kingston Pike between Westwood Drive and Homberg Drive overnight, from 8 p.m. – 6 a.m., beginning Monday, September 16, through mid-October, as work is performed on the water distribution system in the area. One eastbound and one westbound lane of traffic will be maintained at all times, with closed lanes reopening at 6 a.m. each morning. No work will occur overnight Friday and Saturday night. Flaggers and signs will be onsite to assist with traffic control.