January
17, 2020 – KUB’s
contractor, Portland Utilities, began installing sections of new water main on
Boggs Avenue this past week. Crews will continue work west on Boggs Avenue with
daily road closures in the immediate work zone daily from 7:30 a.m. – 6 p.m.
next week. Crews are also scheduled to start saw-cutting roadway asphalt and
installing water main on the section of Davenport Road between Boggs Avenue and
Kingland Avenue next week. This work will require daily road closures between 9
a.m. – 3 p.m. Access to driveways will be maintained.
Friday, January 17, 2020
Concord Street Wastewater Project
January
17, 2020 – KUB’s
contractor, Morgan Construction, is scheduled to begin mobilization the week of
January 27. As a reminder, due to the location of wastewater pipes and manholes
under the roadway, temporary lane shifts will be needed in the immediate area
where crews for the duration of this project. This project is scheduled for
completion by late March 2020.
Holston-Chilhowee Area Wastewater Project (Mini-basin 20A3)
January
17, 2020 – KUB’s
contractor for this project, Morgan Construction, is scheduled to begin
mobilization and pre-construction activities the week of January 20. As a
reminder, due to the location of some wastewater pipes and manholes under area
roadways, temporary lane and/or road closures may be needed in the immediate
area where crews are working for the duration of this project. This project is
scheduled for completion by December 2020.
Old Kingston Pike Wastewater Project
January 17, 2020 – Construction notice postcards were mailed to
customers in the Old Kingston Pike earlier this week. KUB’s contractor for this
project, Hurst Excavating, is scheduled to begin mobilization and
pre-construction activities in the area the week of January 20. As a reminder,
due to the location of some wastewater pipes and manholes under the roadway,
temporary lane and/or road closures may be needed in the immediate area where
crews are working for the duration of this project. This project is scheduled
for completion by late April 2020. Final overall paving and restoration will
take place at the conclusion of the wastewater project.
Fountain City Natural Gas Project
January 17, 2020
– Contractor Classic City Mechanical will work in the following areas next
week:
- Customer service line
connections to the new natural gas mains in the following areas:
- 6141 Weems Road
- 5617, 5628, 5720 Ridgewood
Road
- 3004-3116 Edonia Drive
- 2901-2949 Walkup Drive
- 5900 Van Horn Road
Holston Hills Natural Gas Project
January 17, 2020 Update – Contractor
East Tennessee Pipeline crews will work in the following areas next week:
- Customer service line
connections to the new natural gas main in the following areas:
- 1212, 1300 S. Chilhowee Drive
- 5107, 5109, 5111, 5115, 5119,
5121, 5125 Green Valley Drive
- 5111, 5115 Wyndcroft Drive
Sequoyah Hills Wastewater Project
January 17, 2020 UPDATE - Construction crews will work in the following areas next week
with intermittent road closures between 7 a.m. – 5 p.m.:
- Taliluna
Avenue between South Garden Road and Lakeland Drive
- Whitlow Avenue between Bluff View Road and Cedarhill Road
Closed-circuit
Television Inspection – Crews will continue to work throughout the Phase 2 area next
week. Temporary lane closures will be implemented as needed when crews are
present.
Manhole
Rehabilitation – Crews will work throughout the Phase 2 area next week.
Temporary lane closures will be implemented as needed when crews are present.
Sequoyah
Park –
Break-down of bypass pumping equipment and piping is nearing completion in the
park. Cleanup and restoration of excavated areas will continue as weather
allows over the next several weeks. See the attached map showing current work
corridors within the park. The park, all entrances and parking areas, and boat
ramp remain open during this work. Morgan Construction continues to maintain a
fenced area in the middle parking lot for equipment and materials storage. KUB
has coordinated work in the park with City of Knoxville Parks and Recreation
and the Kingston Pike Sequoyah Hills Association. Informational banners have
been placed in the park entrances/parking areas to provide park visitors with
details about the wastewater rehabilitation work. Updates on the progress of
work in the park will be posted weekly and as needed on this blog site.
Natural
Gas System Work – Crews are scheduled to resume natural gas inspection and
maintenance work at various locations throughout Sequoyah Hills in February.
This work may require short term traffic impacts in the immediate area where
crews are working.
Subscribe to:
Posts (Atom)