Depot Avenue Water Line Project

February 16, 2018 UPDATE – Garney Construction crews continued installation of the 36-inch water main along Blackstock Avenue, between Oak Avenue and Van Street. Work will continue in this area through next week. Crews will also perform saw cutting of asphalt on Williams Street (February 19), E. Depot Avenue (February 19-22), and Morgan Street (February 22-23). This work will require intermittent daily lane closures in the immediate work area. Flaggers will be present to assist with traffic flow in these areas. Paving work continues on the section of Blackstock Avenue between Tulip Avenue and Oak Avenue.