16, 2018 UPDATE –
Hurst Excavating crews installed 442 Ft of 8" sewer main, replaced two
manholes, and renewed six customer services laterals in the 400 and 600 block
of Scenic Drive this past week. Next week, crews will continue work in the 600
block and begin work in the 700 block of Scenic Drive. Toward the end of next
week, one crew will begin work in the utility easement between Alta Vista Way
and Scenic Drive. Weather permitting, and pending completion of work in the 600
and 700 block of Scenic Drive, the contractor will shift the work zone to the
1100 block of Southgate Road, near Sequoyah Library. An updated map will be
issued prior to work shifting to this area.
Restoration and paving crews will begin working next week in the 400
block of Scenic Drive and work their way south.