February 16, 2018 UPDATE – Hurst Excavating crews installed 442 Ft of 8" sewer main, replaced two manholes, and renewed six customer services laterals in the 400 and 600 block of Scenic Drive this past week. Next week, crews will continue work in the 600 block and begin work in the 700 block of Scenic Drive. Toward the end of next week, one crew will begin work in the utility easement between Alta Vista Way and Scenic Drive. Weather permitting, and pending completion of work in the 600 and 700 block of Scenic Drive, the contractor will shift the work zone to the 1100 block of Southgate Road, near Sequoyah Library. An updated map will be issued prior to work shifting to this area.  Restoration and paving crews will begin working next week in the 400 block of Scenic Drive and work their way south.