February 23, 2018 UPDATE – Contractor Cleary Construction continued working on clearing the ROW in the areas noted on the project map. Crews also continued to mobilize equipment and materials to the jobsite. Site clearing and mobilization will continue through early March. Next week, crews will begin connecting sections of pipe above ground in the utility right-of-way in preparation for installation in early March.