Friday, March 9, 2018

Depot Avenue Water Line Project

March 9, 2018 UPDATE – Garney Construction crews continued installation of the 36-inch water main along Van Street this week. The road closure remains in effect in this area. Restoration crews also finished roadway and sidewalk repairs on the section of Blackstock Avenue between Oak Avenue and Van Street. Van Street remains closed to through traffic between Blackstock Avenue and W. Fifth Avenue, but access to businesses and driveways remains open. Crews also continue to work on the bore to install a section of pipe under Second Creek. Equipment for this work is set up off the roadway beneath the W. Fifth Avenue bridge to the west of Cooper Street. In the next several weeks, crews will also begin construction prep work to cross under Second Creek with pipe and along W. Fifth Avenue (between Cooper Street and N. Broadway). Information about work in those areas will be communicated as details are finalized.

No comments:

Post a Comment