March 16, 2018 UPDATE – KUB Underground construction crews continued work on Ainsworth Drive, Corteland Drive and Sheffield Drive this past week. Crews will work in the 7900 and 8400 blocks of Corteland Drive, the 7800 block of Sheffield Drive, and along Ainsworth Drive and Bathurst Road next week.