Friday, March 16, 2018

Depot Avenue Waterline Project

March 16, 2018 UPDATE – Garney Construction crews completed installation of the 36-inch water main on Van Street this week. The road closure will remain in effect on Van Street next week as paving and restoration crews work in the area. Contractor construction crews will move to the area beneath the W. Fifth Avenue bridge (to the west of Cooper Street) as they cross under Second Creek with the 36-inch main. Crews also continue to work on the bore to install sections of pipe under the railroad tracks in this same area beneath the bridge. Upon completion of the Second Creek crossing, plans are to move to W. Fifth Avenue (between Cooper Street and N. Broadway) in late March to begin saw cutting asphalt in preparation for construction in that area. Additional information about the scope of work and traffic impacts on W. Fifth Avenue will be communicated as details are finalized.