Friday, March 2, 2018
South Knox Natural Gas Project
March 2, 2018 UPDATE – Contractor Cleary Construction continued working on clearing the right-of-way in the areas noted on the project map. Crews also continued to mobilize equipment and materials to the jobsite. Next week, contractor crews will begin connecting sections of pipe above ground and staging pipe along the cleared sections of right-of-way in preparation for the start of excavation. Site clearing and mobilization will continue through early March. The first pipeline installation crossing of the roadway at 304 Tipton Station Road is currently scheduled for mid-March. Detailed information on traffic impacts and updated maps will be posted on this blog prior to the start of work in that area.