Friday, May 11, 2018

Depot Avenue Water Main Project

May 11, 2018 UPDATE – Garney Construction and subcontractor crews worked along the section of Williams Street between W. Fifth Avenue and Hudson Alley to install an eight-inch water main this past week. This section of Williams Street will remain closed through next Friday as service lines are connected to the new main and final tie-ins are completed. Next week, crews will continue work on the 36-inch main crossing beneath the W. Fifth Avenue Bridge in the off-road parking lot easement at the corner of Cooper Street and W. Fifth Avenue. Crews will also connect sections of 16-inch and 8-inch mains at the W. Fifth Avenue and Williams Street intersection and the W. Fifth Avenue and N. Gay Street intersection. Crews working from east to west will implement daily single lane closures only in the immediate work zone along short sections of W. Fifth Avenue between N. Broadway and Cooper Street as customer lines are connected to the 12-inch water main recently installed in this area.