Friday, May 18, 2018

South Knox Natural Gas Project


May 18, 2018 UPDATE – Contractor Cleary Construction crews continued work in the off-road areas near Henry Haynes Road. Next week, crews will focus on the area south of Henry Haynes Road in preparation for installation of the pipeline across the road in this area. No road closures are scheduled for next week; however, plans at this time are to close a short section of Henry Haynes Road May 29-30 to install pipeline under the roadway. Additional information will be provided to area residents next week, as this work is finalized. Crews will also work in off-road easements between Henry Haynes Road and W. Marine Road next week. No work will be performed, and all lanes and roads will be reopened, over the Memorial Day holiday.