Friday, May 18, 2018

Sequoyah Hills Wastewater Project


May 18, 2018 UPDATE – This past week, Hurst Excavating subcontractor crews continued work in the off-road easement along back property lines between Alta Vista Way and Valencia Road. Restoration crews are scheduled to work in this area next week. There are no traffic impacts for work in off-road easement areas. Crews will maintain the road closure on Valencia Road between Noelton Drive and Alta Vista Way for wastewater main rehabilitation the week of May 21-25. Driveways will continue to be accessible. Crews will also rehabilitate and test manholes in off-road, back lot easements at the south end of Blows Ferry Road.  Paving and restoration will continue to work on the south end of Mellen Drive and Cherokee Boulevard (near the Southgate Road intersection). Temporary lane closures with alternating traffic flow will be used in the immediate work zone where paving crews are present. No work will be performed, and all lanes and roads will be reopened, over the Memorial Day holiday.