Friday, May 4, 2018

Sequoyah Hills Wastewater Project


SEQUOYAH HILLS May 4, 2018 UPDATE – This past week, crews finished installation of a manhole on Taliluna Avenue west of the Southgate Road intersection, and work on short sections of Scenic Drive and Cherokee Trail. Hurst Excavating subcontractor crews will work in the off-road easement along back property lines between Alta Vista Way and Valencia Road through May 11. There will be no traffic impacts for work in this area. Paving and restoration crews are scheduled to work on the south end of Mellen Drive, and short sections of Scenic Drive, Taliluna Avenue, Cherokee Boulevard, and Kenesaw Avenue next week. Temporary lane closures with alternating traffic flow will be used in the immediate work zone where paving crews are present. 

No comments:

Post a Comment