Friday, May 4, 2018

South Knox Natural Gas Project


May 4, 2018 UPDATE – Pipeline installation continues in the off-road areas progressing north from Tipton Station Road toward Henry Haynes Road. Grading work will also take place in off-road easements on the south side of Tipton Station Road. No long-term road closures are scheduled for next week; however, there may be temporary traffic delays on area roads as trucks with trailers transport large sections of pipe from the contractor laydown finalized in advance of all remaining road closures. 

No comments:

Post a Comment