September 7, 2018 UPDATE – Weekly Update: Garney Construction Crews
completed installation of the 36-inch water main in the Depot Avenue at N.
Central Street intersection this week. The intersection has been paved and was
reopened to normal traffic flow as of Friday morning, September 7. Installation
of the 36-inch main will continue to progress east on the section of E. Depot
Avenue between N. Central Street and Morgan Street next week. E. Depot Avenue
will remain closed to through traffic until Friday, September 14. Crews are
scheduled to start work in the E. Depot Avenue at Morgan Street intersection
starting Tuesday, September 11. Installation of the 36-inch main will continue
south on Morgan Street to E. Jackson Avenue once work in the intersection is
completed.