South Knox Natural Gas Project

September 14, 2018 UPDATE – Pipeline – Cleary Construction’s subcontractors will continue with right-of-way restoration in the area between W. Marine Road and Henry Haynes Road next week. Weather dependent, the entire pipeline installation corridor will be re-seeded from Tipton Station Road to Chapman Highway in the next couple of weeks. No road closures are planned for next week. Gate Station – KUB contractor Cenergy continued installation of the foundations and conduit for the new South Knox Gate Station this past week. Foundation work is approximately 75 percent complete. Work will continue onsite next week with delivery and installation of fabrication components. Motorists should continue to use caution when traveling in the area near 304 Tipton Station Road as construction continues and heavy trucks enter and exit the work area.