September 14, 2018 UPDATE – Pipeline –
Cleary Construction’s subcontractors will continue with right-of-way
restoration in the area between W. Marine Road and Henry Haynes Road next
week. Weather dependent, the entire pipeline installation corridor will be
re-seeded from Tipton Station Road to Chapman Highway in the next couple of weeks.
No road closures are planned for next week. Gate Station
– KUB contractor
Cenergy continued installation of the foundations and conduit for the new South
Knox Gate Station this past week. Foundation work is approximately 75
percent complete. Work will continue onsite next week with delivery and
installation of fabrication components. Motorists should continue to use
caution when traveling in the area near 304 Tipton Station Road as construction
continues and heavy trucks enter and exit the work area.