September 28, 2018 UPDATE – Pipeline –
Cleary Construction’s subcontractors were unable to complete right-of-way restoration
in the pipeline installation area due to weather. Restoration work will
continue in the area between W. Marine Road and Henry Haynes Road as weather
and soil conditions improve. Gate Station
– KUB contractor
Cenergy continued stalling wiring conduit and pre-fabricating piping this week.
Work will continue on those components through next week. Motorists should
continue to use caution when traveling in the area near 304 Tipton Station Road
as construction continues and heavy trucks enter and exit the work area.