Gate Station
– KUB contractor
Cenergy continued installation of the foundations and conduit for the new South
Knox Gate Station this past week. Work will continue onsite next week with
prefabricated piping deliveries. Motorists should continue to use caution
when traveling in the area near 304 Tipton Station Road as construction
continues and heavy trucks enter and exit the work area. Heavier-than-normal
truck traffic is expected during the week of September 10 as Cenergy is
scheduled to deliver three large equipment skids to the new gate station site.
Crews will also set up a materials fabrication area on the north side of Tipton
Station Road, across from the gate station construction site.
Friday, September 7, 2018
South Knox Natural Gas Project
September 7, 2018 UPDATE – Pipeline –
Cleary Construction’s subcontractors will continue with right-of-way
restoration in the area between W. Marine Road and Henry Haynes Road next
week. Weather dependent, the entire pipeline installation corridor will be
re-seeded from Tipton Station Road to Chapman Highway in the next couple of
weeks. Roadway surface restoration was also completed on Tipton Station Road,
Henry Haynes Road, and W. Marine Road this past week. No road closures are
planned for next week.