Friday, September 21, 2018

South Knox Natural Gas Project

September 21, 2018 UPDATE – Pipeline – Cleary Construction’s subcontractors continue with right-of-way restoration in the pipeline installation area. This work is expected to be completed by early October.

Gate Station – KUB contractor Cenergy installed three major station equipment components this week. The contractor will focus on installing wiring conduit and pre-fabricating piping through the end of September. Motorists should continue to use caution when traveling in the area near 304 Tipton Station Road as construction continues and heavy trucks enter and exit the work area.