Friday, December 15, 2017

West Hills Area Natural Gas Project

December 15, 2017 West Hills Area Natural Gas Main Replacement Project Update – This past week, KUB Underground Construction Crews (UGC) continued connecting customer service lines to the new natural gas main in 7600 and 7700 blocks of Bennington Drive.

Crews will continue connecting services lines in the same area next week.

Crews will work in the area up to December 20, with no work performed from December 21-25. Construction will resume on December 26.

As a reminder, this project is scheduled to be completed in four zones over the next 18-24 months. Please see the Project Information Sheet & Map in the column to the right for more details related to this project.

This work may require temporary lane closures in the immediate work zone. Motorists and residents are also reminded to watch for the presence of workers, equipment, and vehicles in the area.

KUB will post weekly updates on this blog for the duration of the project.

Friday, December 8, 2017

West Hills Area Natural Gas Project

December 8, 2017 West Hills Area Natural Gas Main Replacement Project Update – This past week, KUB Underground Construction Crews (UGC) worked on connecting customer service lines to the new natural gas main in 7600 and 7700 blocks of Bennington Drive.

Crews will continue connecting services lines in the same area next week, with plans of progressing to the 7800 block of Sheffield Drive.

A second KUB crew continued to bore in sections of new natural main on Corteland Drive this week, completing installation between Bennington Drive and Sheffield Drive. This crew will continue to work on Corteland Drive, from Sheffield Drive to Marlboro Road, next week.

Crews will work in the area up to December 20, with no work performed from December 21-25. Construction will resume on December 26.

As a reminder, this project is scheduled to be completed in four zones over the next 18-24 months. Please see the Project Information Sheet & Map in the column to the right for more details related to this project.

This work may require temporary lane closures in the immediate work zone. Motorists and residents are also reminded to watch for the presence of workers, equipment, and vehicles in the area.

KUB will post weekly updates on this blog for the duration of the project.

Thursday, December 7, 2017

Sequoyah Hills Area Wastewater Rehabilitation Project

December 7, 2017 UPDATE – As a follow-up to letters mailed to customers on November 17, the projected start date for construction on Phase 1 on the Sequoyah Hills Area Wastewater Rehabilitation Project has shifted to early January 2018. Also, please see the correct phone numbers for designated KUB Customer Support contacts for this project below (contact weekdays between 7 a.m. - 4 p.m.):
· Tim Cox – (865) 558-2947 [office] or 313-3777 [cell]
· Tom England – (865) 558-2177 [office], or 640-3157 [cell]

Mr. England’s phone numbers were incorrectly listed in the November 17 letter. We apologize for any confusion.

Please continue to follow this blog for project updates.

Friday, December 1, 2017

West Hills Area Natural Gas Project

December 1, 2017 West Hills Area Natural Gas Main Replacement Project Update – This past week, KUB Underground Construction Crews (UGC) completed tie-up work to connect sections of newly installed natural gas main on Vanosdale Road.

Crews will begin connecting customer service lines to the new main on Bennington Drive next week.

A second KUB crew worked to bore in sections of new natural main on Corteland Drive this week, and they are scheduled to resume work in that area again next week.

As a reminder, this project is scheduled to be completed in four zones over the next 18-24 months. Please see the Project Information Sheet & Map in the column to the right for more details related to this project.

This work may require temporary lane closures in the immediate work zone. Motorists and residents are also reminded to watch for the presence of workers, equipment, and vehicles in the area.

KUB will post weekly updates on this blog for the duration of the project.

Friday, November 17, 2017

West Hills Area Natural Gas Project

November 17, 2017 West Hills Area Natural Gas Main Replacement Project Update – This past week, KUB Underground Construction Crews (UGC) continued tie-up work to connect sections of newly installed natural gas main on Sheffield Drive.

Crews will resume tie-up work on Vanosdale Road next week, and then proceed to connecting customer service lines on Bennington Drive and Sheffield Drive.

Crews will not work next Thursday and Friday, November 23-24, due to the Thanksgiving holiday. Work will resume on Monday, November 27.

As a reminder, this project is scheduled to be completed in four zones over the next 18-24 months. Please see the Project Information Sheet & Map in the column to the right for more details related to this project.

This work may require temporary lane closures in the immediate work zone. Motorists and residents are also reminded to watch for the presence of workers, equipment, and vehicles in the area.

KUB will post weekly updates on this blog for the duration of the project.

Friday, November 10, 2017

West Hills Area Natural Gas Project

November 10, 2017 West Hills Area Natural Gas Main Replacement Project Update – This past week, KUB Underground Construction Crews (UGC) completed tie-up work to connect sections of newly installed natural gas main in the 7600 block of Sheffield Drive.

Crews continued to bore in new pipe on Vanosdale Road through the end of the week. The tie-up crew will move to this area on Monday, November 13, weather permitting. Once the sections of main are connected on Vanosdale Road, it will provide an additional natural gas feed into the subdivision.

Crews are also scheduled to begin connecting customer service lines to the new main over on Bennington Drive and Sheffield Drive during the next couple of weeks.

As a reminder, this project is scheduled to be completed in four zones over the next 18-24 months. Please see the Project Information Sheet & Map in the column to the right for more details related to this project.

This work may require temporary lane closures in the immediate work zone. Motorists and residents are also reminded to watch for the presence of workers, equipment, and vehicles in the area.

KUB will post weekly updates on this blog for the duration of the project.

Friday, November 3, 2017

West Hills Area Natural Gas Project

November 3, 2017 West Hills Area Natural Gas Main Replacement Project Update – KUB Underground Construction Crews (UGC) are scheduled to resume boring and tie-in work in the Bennington Drive, Vanosdale Road, and Corteland Drive areas next week.

As a reminder, this project is scheduled to be completed in four zones over the next 18-24 months. Please see the Project Information Sheet & Map in the column to the right for more details related to this project.

This work may require temporary lane closures in the immediate work zone. Motorists and residents are also reminded to watch for the presence of workers, equipment, and vehicles in the area.

KUB will post weekly updates on this blog for the duration of the project.