September 13,
2019 Update –Contractor
East Tennessee Pipeline crews will directional bore to install new natural gas
main from the 5500 block east to the 5800 block on Holston Hills Road. Crews
will also bore across Holston Hills Road at Cliffside Lane and continue with
installation of 225-feet of main on that street. Customer service line
connections will be made between the 5900 and 5300 blocks on E. Sunset Drive.

Friday, September 13, 2019
Homberg Drive/Kingston Pike Water Main Project
HOMBERG DRIVE
WATER MAIN REPLACEMENT – September 13, 2019 – All water main installation, service
line connection, and paving/restoration has been completed on Homberg Drive, S.
Mohican Street, and Whitaker Drive.
KINGSTON PIKE WATER MAIN REPLACEMENT – September 13, 2019 – Pre-construction work, including saw-cutting asphalt in
preparation for digging, was completed overnight this past Wednesday and
Thursday. KUB Underground Construction crews are scheduled to begin excavation
work at the intersection of Homberg Drive and Kingston Pike at 8 p.m., Sunday,
September 15. As a reminder, this work will be performed overnight from 8
p.m.—6 a.m. through mid-October. The center turn lane will be closed
continuously for the duration of the project on the section of Kingston Pike
between Westwood Road and Homberg Drive. Additional lane closures will be
needed as work shifts to different areas on this section of Kingston Pike. One
eastbound and one westbound lane of traffic will be maintained at all times,
with closed lanes reopening at 6 a.m. each morning. No work will occur
overnight Friday and Saturday night. Flaggers and signs will be onsite to
assist with traffic control.
(Bearden
Area) Kingston Pike Lane Closures [Overnight, September 16 – Mid October] – KUB crews will implement
lane closures of both the eastbound and westbound lanes of Kingston Pike
between Westwood Drive and Homberg Drive overnight, from 8 p.m. – 6 a.m.,
beginning Monday, September 16, through mid-October, as work is performed on
the water distribution system in the area. One eastbound and one westbound lane
of traffic will be maintained at all times, with closed lanes reopening at 6
a.m. each morning. No work will occur overnight Friday and Saturday night. Flaggers
and signs will be onsite to assist with traffic control.
Fountain City Natural Gas Project
September 13,
2019 – Contractor
Classic City Mechanical connected customer service lines to the new natural gas
main on Martha Berry Drive and bored in new sections of main on Mynatt Drive
this week. Next week, crews will work on connecting customer service lines on
Grove Drive, from Martha Berry Drive toward Mynatt Road. A boring crew will
also work on Grove Drive, progressing toward Edonia Road.
Friday, September 6, 2019
Sequoyah Hills Wastewater Project
Sequoyah
Hills Wastewater Rehabilitation – Construction crews will work in the following areas next week
with intermittent road closures between 7 a.m. – 5 p.m.:
·
Agawela Avenue between
Taliluna Avenue and Cherokee Boulevard
Crews
will also work on the following roads with intermittent lane closures
between 7 a.m. – 5 p.m.
·
Taliluna Avenue
between Agawela Avenue and Southgate Road
·
Kenesaw Avenue between
Taliluna Avenue and Cherokee Boulevard
Crews
will also work in the following off-road easements with minimal traffic
impacts:
·
Easement between
Agawela Avenue and Kenesaw Avenue in Sequoyah Village Apartments (Restoration)
·
Easement between
Iskagna Drive and Woodland Drive (Restoration)
Closed-circuit
Television Inspection – Crews will continue to work throughout the Phase 2 area next
week. Temporary lane closures will be implemented as needed when crews are
present.
Sequoyah
Park –
Morgan Construction and their subcontractors continue to rehabilitate the
existing wastewater main and manholes in Sequoyah Park. See the attached map
showing current work corridors within the park. The park, all entrances and
parking areas, and boat ramp remain open during this work. Morgan Construction
is also maintaining a fenced area in the middle parking lot for equipment and
materials storage. KUB has coordinated work in the park with City of Knoxville
Parks and Recreation and the Kingston Pike Sequoyah Hills Association.
Informational banners have been placed in the park entrances/parking areas to
provide park visitors with details about the wastewater rehabilitation work.
Updates on the progress of work in the park will be posted weekly and as needed
on this blog site.
Natural
Gas System Work – Crews have resumed natural gas inspection and maintenance
work at various locations throughout Sequoyah Hills. This work may require
short term traffic impacts in the immediate area where crews are working.
Holston Hills Natural Gas Project
September
6, 2019 Update –Contractor East Tennessee Pipeline crews are
currently working to connect customer service lines to the new natural gas main
between 5908 and 5400 E. Sunset Drive. Next week, crews will be performing
potholing work to locate existing buried utility lines and boring in new
sections of natural gas main between the 5500 block of Holston Hills Road and
the Crestwood Drive intersection. Crews will also pothole and bore along
Cliffside Lane, starting at the Holston Hills Road intersection
Fountain City Natural Gas Project
September 6,
2019 – Contractor
Classic City Mechanical bored in new natural gas main on Martha Berry Drive to
Rifle Range Road. Next week, crews will bore in new sections of natural gas
main on Mynatt Road, and perform potholing work to locate existing buried
utility lines on Grove Drive, between Martha Berry Drive and Edonia Drive.
Homberg Drive Water Main Project
September 6, 2019 – KUB Underground Construction crews have
completed service line connections, and asphalt repairs. Work will now shift to
the 5500 block of Kingston Pike, between Westwood Drive and Homberg Drive.
(Bearden
Area) Kingston Pike Lane Closures [Overnight, September 11-30] – KUB crews will implement
lane closures of both the eastbound and westbound lanes of Kingston Pike between
Westwood Drive and Homberg Drive overnight, from 8 p.m. – 6 a.m., beginning
Wednesday, September 11, through Monday, September 30, as work is performed on
the water distribution system in the area. One eastbound and one westbound lane
of traffic will be maintained at all times, with closed lanes reopening at 6
a.m. each morning. No work will occur overnight Friday and Saturday night.
Flaggers and signs will be onsite to assist with traffic control.