Depot Avenue Water Line Project
June
22, 2018 UPDATE –
Garney Construction and subcontractor crews completed installation of the
36-inch water main on W. Fifth Avenue through the N. Broadway intersection this
week. Paving and restoration work has been completed and the N. Broadway
intersection has been reopened to normal traffic flow. Crews have shifted the
work zone to the area between the N. Gay Street intersection and Williams
Street. The N. Gay Street intersection will remain closed through next week.
Alternate routes around the intersection closure include N. Broadway, Emory
Place, King Street, S. Central Street, W. Depot Avenue, and Cooper Street.