Friday, June 22, 2018

West Hills Natural Gas Project


June 22, 2018 UPDATE –  ZONE 2: KUB contractor Classic City Mechanical worked in the 8100 block of Bennington Drive this week. Crews will continue to work between 8117 through the 8300 block of Bennington Drive next week. ZONE 3: Crews from KUB Underground Construction and East Tennessee Pipeline have completed all customer service line connections in this zone except for remaining houses in the 500 and 600 blocks of Broome Road. Crews will work in that area next week. ZONE 4: This week, KUB mailed a summer 2018 project update to customers in all four construction zones to advise on the status of the overall project. Please see the attached updated information sheet and overall project map that was included in the mailing for more details. Among the information included in that update mailing was details on the start of pre-construction activities scheduled to begin in Zone 4 next week. Crews will begin work on Rockingham Drive and Downing Drive next Monday, June 25. 5,600 feet of natural gas main and 67 customer service line connections will be installed in this zone.
 

No comments:

Post a Comment