June 29, 2018 UPDATE – Hurst Excavating continued open-cut trench work along Wilani Road this week. Due to extensive excavation, Wilani Road will remain closed continuously to through traffic between Taliluna Avenue and Southgate Road through next week. Access will be maintained to driveways on Wilani Road. Subcontractor pipe-bursting crews also continued work in the vicinity of Calumet Drive and Blows Ferry Road. Pipe-bursting crews will continue work in those areas next week while also starting work on Arrowhead Trail. Restoration and paving work was completed near Shawnee Lane and Valencia Road. Driveway repairs will also continue on Mellen Drive. NOTES: Crews will not work on Wednesday, July 4, in observance of the Independence Day holiday. As indicated on this week’s map, the City of Knoxville is currently working on the stormwater system on Noelton Drive and Hiawatha Drive. This is not part of KUB’s work in the area. Please contact the City of Knoxville at 311 for more information about their work in this area. 

(Sequoyah Hills) Sequoyah Hills Area Road Closures [Extended, July 2-6] – KUB contract crews will implement the below road closures as needed daily, Monday-Friday, from 7 a.m. – 5 p.m., July 2-6, as work continues on the wastewater collection system in the area:
·         Arrowhead Trail between Blows Ferry Road and Lyons View Pike
·         Arrowhead Trail between Blows Ferry Road and Dogwood Lane
·         Blows Ferry Road between Arrowhead Trail and Calumet Drive
Reminder that Wilani Road between Southgate Road and Taliluna Avenue will remain closed continuously through July 6 due to extensive excavation. Access to local businesses and area homes will be maintained, and flaggers and signs will be on site to assist with traffic control. Roadways will be re-opened outside of work hours.  Follow-up advisories will be issued as necessary. 