June 14, 2018 UPDATE – Garney Construction and subcontractor crews continued installation of the 36-inch water main on the section of W. Fifth Avenue between Queen Street and N. Gay Street. Crews will continue to work in this zone through June 22. The N. Gay Street intersection remains open. Next week, Garney Construction will have a crew working on a wastewater manhole in an off-road easement in the Blackstock Avenue area behind The International. There will be no traffic impacts related to this work. Work is expected to continue in this area through mid-June.