South Knox Natural Gas Project


June 22, 2018 UPDATE – Cleary Construction crews completed installation of the new natural gas main under the roadway at W. Marine Road. That section of W. Marine Road, and the access road to the Food City store, are reopened to normal traffic flow. Next week, crews will continue installation of the new natural gas main in the easement on the west side of Smoky Grove Road. Additionally, crews will implement a full road closure on Mountain Grove Road (just west of the Smoky Grove Road intersection) starting at 7 a.m. Monday, June 25, and lasting through 5 p.m. Friday, June 29, to allow for pipeline installation under the roadway in this area. Cleary Construction will also close the southbound, righthand turn lane on Chapman Highway (between the IHOP/CVS entrance and Mountain Grove Road) starting Monday, June 25, and lasting through Friday, August 3. Off-road easement restoration will also continue between W. Marine Road and Tipton Station Road over the next several weeks. GATE STATION UPDATE: Beginning Thursday, June 28, KUB subcontractor Blount Excavation will begin site preparation work, including vegetation clearing and grading activities, in preparation for construction of the new natural gas gate station located at 304 Tipton Station Road. There are no current lane or road closures in association with this work; however, there will be an increase in heavy truck and equipment traffic in this area.

TRAFFIC ADVISORIES

(South Knoxville) Chapman Highway Continuous Lane Closure [June 25 – August 3] – KUB contract crews will close a short section of the southbound right turn lane of Chapman Highway beginning at IHOP/CVS to Mountain Grove Drive, from 7 a.m., Monday, June 25, through 5 p.m., Friday, August 3, as work is performed on the natural gas distribution system in the in the area. Both southbound lanes, the center turn lane, and both northbound lanes will remain open during this time and turn access to Mountain Grove Drive will be maintained. Access to local business will be maintained, and flaggers and signs will be on site to assist with traffic control.

(South Knoxville) Mountain Grove Drive Road Closure [June 25-29] – KUB contract crews will implement a road closure on Mountain Grove Drive between Majestic Grove Road and Chapman Highway from 7 a.m., Monday, June 25, through 5 p.m., Friday, June 29, as work is performed on the natural gas distribution system in the area. Alternate routes include W. Marine Road, W. Governor John Sevier Highway, and Majestic Grove Road. Flaggers and signs will be on site to assist with traffic control. Follow-up advisories will be issued as necessary. 

No comments:

Post a Comment