Friday, June 22, 2018

Sequoyah Hills Wastewater Project

June 22, 2018 UPDATE – Hurst Excavating began open-cut trench work along Wilani Road this week. Due to extensive excavation, Wilani Road will remain closed continuously to through traffic between Taliluna Avenue and Southgate Road through the end of June. Access will be maintained to driveways on Wilani Road. Subcontractor pipe-bursting crews completed work along Calumet Drive and in the off-road easements between Calumet Drive and Blows Ferry Road. Restoration and paving work will continue on Calumet Drive, Mellen Road (driveway at the south end), and Valencia Road next week. Work will also continue in the off-road easement near Shawnee Lane through next week. Crews will also expand the work zone next week to include the area near the Arrowhead Trail and Blows Ferry Road intersection. Road closures will be necessary in this area, as well, to facilitate access for construction equipment.

TRAFFIC ADVISORY

(Sequoyah Hills) Sequoyah Hills Area Road Closures [June 25-29] – KUB contract crews will implement the below road closures daily, Monday-Friday, from 7 a.m. – 5 p.m., June 25-29, as work continues on the wastewater collection system in the area:

  • Arrowhead Trail between Blows Ferry Road and Lyons View Pike
  • Arrowhead Trail between Blows Ferry Road and Dogwood Lane
  • Blows Ferry Road between Arrowhead Trail and Calumet Drive
Access to local businesses and area homes will be maintained, and flaggers and signs will be on site to assist with traffic control. Roadways will be re-opened outside of work hours.  Follow-up advisories will be issued as necessary. 