October 11, 2019 – KUB contractor crews began saw cutting
on the eastern end of Old Kingston Pike this past Wednesday, October 9. Saw
cutting and construction prep work is expected to conclude early next
week. The areas being saw cut include Old Kingston Pike, S. Forest Park
Boulevard, and Staub Street. Expect daily lane and road closures in the
immediate areas where crews are working during this time. Detours and alternate
routes will be provided to maintain access to all business in the construction
zone. KUB Underground Construction crews are scheduled to begin
construction activity to install the new water main on Wednesday, October
16. Construction will begin at the eastern end of Old Kingston Pike and
progress west. Construction zones in the coming weeks will include S. Forest
Park Boulevard, and Staub Street. Water
main replacement is scheduled to last through early January 2020 in this area.
To minimize future disruptions in this area, KUB will follow the water main
project with wastewater collection system upgrades in this same area starting
in early January. Final paving and restoration will take place at the
conclusion of the wastewater project.
Friday, October 11, 2019
Fountain City Natural Gas Project
October 11,
2019 – Contractor
Classic City Mechanical will work in the following areas next week:
- Potholing to locate existing
buried utilities and boring in sections of new natural gas main on Grove
Park Drive from Edonia Drive to Walkup Drive
- Potholing to locate existing
buried utilities and boring in sections of new natural gas main on Walkup
Drive from Grove Park Drive to Cub Lane
- Potholing to locate existing
buried utilities and boring in sections of new natural gas main on Gresham
Road from Ballard Lane to 808 Gresham Road
- Connecting sections of bored-in
natural gas main on Grove Drive from Medlin Heights Road to Gresham Road
Holston Hills Natural Gas Project
October 11,
2019 Update –Contractor
East Tennessee Pipeline crews will work in the following areas next week:
- Directional boring to install
sections of new natural gas main from the 5600 block of Crestwood Drive to
the Holston Hills Road intersection
- Potholing to locate existing
buried utility lines between the Green Valley Drive/S. Chilhowee Drive
intersection to Shady Dell Trail
- Connect customer service lines
to the new natural gas main between 5509 and 5404 Crestwood Drive
- Connect customer service lines
to the new natural gas main between 5405 and 5507 Holston Hills Road
Friday, October 4, 2019
Sequoyah Hills Wastewater Project
October
4, 2019 UPDATE – Construction
crews will work in the following areas next week with intermittent road
closures between 7 a.m. – 5 p.m.:
·
Bluff View Road
between Southgate Road and Holloway Drive
·
Kenesaw Avenue between
Taliluna Avenue and Cherokee Boulevard
Crews
will also work in the following off-road easements with minimal traffic
impacts:
·
Easement between South
Garden Road and Taliluna Avenue
Yard/Easement
Restoration – Weather
has had a major impact on yard/easement restoration efforts as recent hot and
dry weather have combined to prevent planted grass seed from taking root and
growing. Next week’s forecast calls for a relief from historically hot
temperatures and dry conditions to a more normal weather pattern. Morgan
Construction and its subcontractors will have crews deployed across the Phase 2
area performing general clean-up and re-planting grass and placing
straw. Restoration may take several weeks, but work will continue until
all construction areas are repaired.
Closed-circuit
Television Inspection – Crews will continue to work throughout the Phase 2 area next
week. Temporary lane closures will be implemented as needed when crews are
present.
Manhole
Rehabilitation – Crews will work throughout the Phase 2 area next week.
Temporary lane closures will be implemented as needed when crews are present.
Sequoyah
Park –
Morgan Construction and their subcontractors continue to rehabilitate the
existing wastewater main and manholes in Sequoyah Park. See the attached map
showing current work corridors within the park. The park, all entrances and
parking areas, and boat ramp remain open during this work. Morgan Construction
is also maintaining a fenced area in the middle parking lot for equipment and
materials storage. KUB has coordinated work in the park with City of Knoxville
Parks and Recreation and the Kingston Pike Sequoyah Hills Association.
Informational banners have been placed in the park entrances/parking areas to
provide park visitors with details about the wastewater rehabilitation work.
Updates on the progress of work in the park will be posted weekly and as needed
on this blog site.
Natural
Gas System Work – Crews have resumed natural gas inspection and maintenance
work at various locations throughout Sequoyah Hills. This work may require
short term traffic impacts in the immediate area where crews are working.
Holston Hills Natural Gas Project
October 4,
2019 Update –Contractor
East Tennessee Pipeline crews will work in the following areas next week:
·
Directional boring to install
sections of new natural gas main, cleaning to remove construction debris from
new main, and testing from the 5600 block of Crestwood Drive to the Holston
Hills Road intersection
·
Connecting customer service lines to
the new natural gas main from 5509 to 5400 Crestwood Drive
·
Finish customer service connections
on Sunset Drive
Fountain City Natural Gas Project
October 4,
2019 – Contractor
Classic City Mechanical will work in the following areas next week:
- Connecting customer service lines to new natural gas main from 1911 to 2108 Martha Berry Drive
- Potholing to locate existing buried utilities and boring in sections of new natural gas main on Grove Drive from Belcourt Drive to Pruden Drive
- Potholing to locate existing buried utilities and boring in sections of new natural gas main on Edonia Drive from Grove Drive to Grove Park Drive
Kingston Pike/Homberg Drive Water Main Project
KINGSTON PIKE WATER MAIN REPLACEMENT – October 4, 2019 – KUB Underground made the final customer
service line connections to the new main this past week. All construction is
now complete, all construction related traffic control measures have been
removed, and normal traffic flow has resumed on the section of Kingston Pike
between Westwood Road and Homberg Drive.
OLD
KINGSTON PIKE WATER MAIN REPLACEMENT – October 4, 2019 – As a continuation of recent water main
replacement projects on Homberg Drive and the section of Kingston Pike between
Homberg Drive and Westwood Road, KUB Underground Construction crews will be
moving to the Old Kingston Pike area next week. Saw-cutting and
pre-construction prep activity is schedule to start on Old Kingston Pike, S.
Forest Boulevard, and Staub Street on Monday, October 7, and last through the
end of the week. Construction will start near the intersection of Kingston Pike
and Old Kingston Pike the week of October 12. Temporary lane and/or road
closures will be required in the immediate areas where crews are working, but
crews will maintain access to driveways and businesses. Water main replacement
is scheduled to last through early January 2020 in this area. To minimize
future disruptions in this area, KUB will follow the water main project with
wastewater collection system upgrades in this same area starting in early
January. Final paving and restoration will take place at the conclusion of the
wastewater project.