October 4, 2019 – Contractor Classic City Mechanical will work in the following areas next week:
  •          Connecting customer service lines to new natural gas main from 1911 to 2108 Martha Berry Drive
  •          Potholing to locate existing buried utilities and boring in sections of new natural gas main on Grove Drive from Belcourt Drive to Pruden Drive
  •          Potholing to locate existing buried utilities and boring in sections of new natural gas main on Edonia Drive from Grove Drive to Grove Park Drive