Fountain City Natural Gas Project

October 11, 2019 – Contractor Classic City Mechanical will work in the following areas next week:
  • Potholing to locate existing buried utilities and boring in sections of new natural gas main on Grove Park Drive from Edonia Drive to Walkup Drive
  • Potholing to locate existing buried utilities and boring in sections of new natural gas main on Walkup Drive from Grove Park Drive to Cub Lane
  • Potholing to locate existing buried utilities and boring in sections of new natural gas main on Gresham Road from Ballard Lane to 808 Gresham Road
  • Connecting sections of bored-in natural gas main on Grove Drive from Medlin Heights Road to Gresham Road