Holston Hills Natural Gas Project

October 11, 2019 Update –Contractor East Tennessee Pipeline crews will work in the following areas next week:
  • Directional boring to install sections of new natural gas main from the 5600 block of Crestwood Drive to the Holston Hills Road intersection
  • Potholing to locate existing buried utility lines between the Green Valley Drive/S. Chilhowee Drive intersection to Shady Dell Trail
  • Connect customer service lines to the new natural gas main between 5509 and 5404 Crestwood Drive
  • Connect customer service lines to the new natural gas main between 5405 and 5507 Holston Hills Road