Friday, August 31, 2018

Depot Avenue Water Line Project

August 31, 2018 UPDATE – Garney Construction Crews continued installation of the 36-inch water main in the Depot Avenue at N. Central Street intersection this week. Due to extensive excavation and the presence of numerous underground pipes in this area, this intersection will remain closed continuously (including nights and weekends) through 5 p.m. Friday, September 7. As indicated on this week’s construction map, alternate routes around the intersection work zone include W. Magnolia Avenue, Morgan Street, and E. Jackson Avenue. Upon completion of work in the intersection, installation of the 36-inch main will continue to progress east onto E. Depot Avenue. Due to the scope of construction in this area, this section of E. Depot Avenue is also currently closed to through traffic. Crews will not work on Monday, September 3, in observance of Labor Day; however, current traffic control measures will remain in place.

No comments: