West Hills Natural Gas Project


August 10, 2018 UPDATE – ZONE 2: KUB contractor Classic City Mechanical worked service reconnections in the 8200 block of Chesterfield Drive, as well as in the 8200 block of Bennington Drive. Next week, they will move to the 8300 block of Bennington Drive, 8200 block of Chesterfield Drive, Westminster Road and the 8200 block of Corteland Drive. ZONE 4: KUB Underground Construction crews, alongside East Tennessee Pipeline crews, worked on service reconnections in the 7400 block of Bennington Drive and the 700 block of Shadycrest Drive. Next week, they will be at the intersection of Vanosdale Road & Bennington Drive, 7200 block of Vanosdale Road and on Shadycrest Lane.