Weekly Update: Cleary Construction crews
will continue work to put the newly-installed pipeline into service, including
placement of enclosures around the new main line valves. No road closures are
scheduled for next week; however, the closure of the righthand turn lane on
Chapman Highway (between the IHOP/CVS entrance and Mountain Grove Road) has
been extended through August 10, as listed on the map. Gate Station:
Blount Excavating crews continued grading work in preparation for installation
of the structural and equipment foundations next week. Periodic temporary lane
closures may be needed in this area of Tipton Station Road as construction
equipment and vehicles enter and exit the work zones.
(South Knoxville) Chapman
Highway Continuous Lane Closure [Extended, August 3-10] – KUB contract crews will maintain a closure of a short section of
the southbound right turn lane of Chapman Highway beginning at IHOP/CVS to
Mountain Grove Drive, from
5 p.m., Friday, August 3, through 5 p.m., Friday, August 10, as work is performed on the natural gas distribution system
in the in the area. Both southbound lanes, the center turn lane, and
both northbound lanes will remain open during this
time and turn access to Mountain Grove Drive will be maintained. Access to local business will be maintained, and flaggers
and signs will be on site to assist with traffic control.