August 23, 2018 UPDATE – Pipeline – Project contractor Cleary Construction
completed work on the pipeline system valve enclosures this week. Next
week, Cleary crews will continue clean-up activities at the equipment and
materials laydown yard near Mountain Grove Drive. Final right-of-way
restoration will continue through the Mountain Grove Drive area to Henry Haynes
Road. Weather permitting, final paving repairs are scheduled for the pipeline
roadway crossing areas on Mountain Grove Drive, W. Marine Road, Henry Haynes
Road, and Tipton Station Road next week. Alternating lane closures will be
needed on the above-mentioned roads in association with paving
repairs. Details for these closures will be communicated as details and
schedules are finalized.
Gate Station
– Contractor Cenergy
continued work this past week to prepare the site for foundation installations. Next
week, concrete will be poured for equipment foundations. Welders will mobilize
next week to begin onsite fabrication of piping. The onsite pipeline
fabrication area will be set up on KUB’s right-of-way north of Tipton Station
Rd.
Additional
note – Beginning
Saturday, August 25, and lasting through Saturday, September 1, KUB’s natural
gas supplier, Enbridge, will be performing tapping operations on the main
located in their right-of-way near 304 Tipton Station Rd.