(South
Knoxville) Chapman Highway Continuous Lane Closure [Extended, August 10-17] – KUB contract crews will maintain a closure of
a short section of the southbound right turn lane of Chapman Highway beginning
at IHOP/CVS to Mountain Grove Drive, from 5 p.m., Friday, August 10, through 5 p.m.,
Friday, August 17, as work is performed on the
natural gas distribution system in the in the area. Both southbound
lanes, the center turn lane, and both northbound lanes will
remain open during this time and turn access to Mountain Grove Drive
will be maintained. Access to local business will be
maintained, and flaggers and signs will be on site to assist with traffic
control.
Friday, August 10, 2018
South Knox Natural Gas Project
August 10, 2018 UPDATE – Cleary Construction crews
will continue placement of enclosures around the new main line valves, as well
as restoration work. No road closures are scheduled for next week; however, the
closure of the righthand turn lane on Chapman Highway (between the IHOP/CVS
entrance and Mountain Grove Road) has been extended through August 17, as
listed on the map. Gate Station: Blount Excavating crews completed
grading work in preparation for installation of the structural and equipment
foundations, and the concrete for the foundations will be poured next week.
Periodic temporary lane closures may be needed in this area of Tipton Station
Road as construction equipment and vehicles enter and exit the work zones.