August 3, 2018 UPDATE – OVERALL PROJECT UPDATE: Phase 1 construction is approximately 50 percent complete as of
early August. This portion of the project remains on schedule for completion by
January 2019. Sewer pipeline and manhole rehabilitation
has been completed on Scenic Drive and Southgate Road, ahead of the City of Knoxville’s
plans to pave those areas in 2019. Scenic and Southgate have already been paved
by the City. The contractor, Hurst Construction, is performing clean-up
and restoration following deep excavation on Wilani Road. Construction on
Arrowhead Trail is nearing completion, to be followed by clean-up and
restoration. Extensive construction remains for Phase
1 work on Alta Vista Way, Noelton Drive, and Hiawatha Drive through this fall.
Phase 2, which includes rehabilitation of seven miles of wastewater lines, is
scheduled to begin in January 2019. Information regarding Phase 2 will be
communicated this fall as details are finalized.
Weekly Update: Hurst Excavating and its
subcontractors will continue clean-up and restoration work on Wilani Road
between Taliluna Avenue and Southgate Road through next Friday, August 10.
Construction will continue on Hiawatha Drive (between Noelton Drive and Towanda
Trail), and pipe-lining and restoration crews will work in the vicinity of
Arrowhead Trail through next week. Construction requiring road closures will
begin next week on Chippewa Circle and Chickasaw Road. Work on Chippewa Circle
will be divided into two sections to maintain access to detour via Shawnee
Lane.
SPECIAL NOTE – SATURDAY WORK: Crews plan to work between the hours of
7 a.m. and 5 p.m. on Saturday, August 4, to install customer service laterals on the 500 block of Arrowhead Trial. Construction may extend beyond 5
p.m., depending on construction progress and conditions encountered during
excavation. This section of Arrowhead Trail will remain closed through traffic
during construction. Access to driveways will be maintained. Appropriate
traffic control measures will be in place to direct traffic flow around the
work zone.
NOTES: COK Stormwater Work – As indicated on this week’s map, the
City of Knoxville is currently working on the stormwater system on Noelton
Drive near the intersection with Alta Vista Way. This is not part of KUB’s work
in the area. Please contact the City of Knoxville at 311 for more information
about their work in this area. Yard Restoration -- KUB and Hurst
Excavating have noticed that grass recently planted as part of yard restoration
has started to turn brown due to hot, dry weather. Those areas will be
readdressed by the contractor as temperatures decrease during the fall growing
season.
(Sequoyah Hills) Sequoyah
Hills Area Road Closures [August 6-10] – KUB contract crews will implement the below
road closures as needed daily,
Monday-Friday, from 7 a.m. – 5 p.m., August 6-10, as
work continues on the wastewater collection system in the area:
- Chippewa Circle at Noelton Drive
- Wilani Road between Southgate Road and Taliluna Avenue
- Alta Vista Way between Blows Ferry Road and Arrowhead Trail
Additionally, Chickasaw
Road between Cherokee Boulevard and Navaho Road will be closed continuously
from 7 a.m., August 6, through 5 p.m., August 10, due to excavation. Access to
area homes will be maintained, and flaggers and signs will be on site to assist
with traffic control. With the exception of Chickasaw Road, all other roadways
in the area will be re-opened outside of work hours. Follow-up advisories will
be issued as necessary.