South Knox Natural Gas Project

August 17, 2018 UPDATE – Cleary Construction crews will continue placement of enclosures around the new main line valves, as well as restoration work. The righthand turn lane on Chapman Highway has been re-opened to normal traffic flow, and there are no road closures scheduled for next week. Gate Station: Blount Excavating crews completed grading work in preparation for installation of the structural and equipment foundations. Work began this past week to pour the concrete foundations. Periodic temporary lane closures may be needed in this area of Tipton Station Road as construction equipment and vehicles enter and exit the gate station work zone.

Site of the new KUB South Knox Gate Station at 304 Tipton Station Road.


Pipeline construction and restoration photos of the same area.