West Hills Natural Gas Project

August 17, 2018 UPDATE – ZONE 2: KUB contractor Classic City Mechanical worked at 409 N. Winston Road and 8301 E. Walker Springs Road this past week. Next week, crews will work on service line connections in the 8200 block of Chesterfield Drive and the 8200 block of Bennington Drive. ZONE 4: KUB and East Tennessee Pipeline crews worked at the intersection of Vanosdale Road & Bennington Drive, the 7200 block of Vanosdale Road, and the 700 block of Shadycrest Lane this past week. Crews will work in the 7100 block of Rockingham Drive and on Dorchester Drive next week.

KUB crews work near the Vanolsdale Road and Bennington Drive intersection the week of August 13.



A KUB field inspector uses GPS equipment to map the location of a newly-installed natural gas pipeline in the West Hills area.