October 30, 2018 UPDATE – The final tie-in for the 8-inch water main requiring the closure
of the W. Depot Avenue at N. Gay Street intersection, originally scheduled for
Wednesday, October 31, has been moved to Thursday, November 1. To
accommodate an event in the area, the intersection will temporarily be reopened
to normal traffic flow starting at 5 p.m., Tuesday, October 30, through 8
a.m., Thursday, November 1. Construction to tie-in the 8-inch main is
expected to be completed during daylight hours on Thursday, and the
intersection will reopen to normal traffic flow by the evening. One final
temporary intersection closure will be necessary at a later date for paving and
restoration. A follow-up notice will be issued as details and the schedule are
finalized for that temporary intersection closure.

Tuesday, October 30, 2018
Monday, October 29, 2018
Jackson Avenue Ramps Utility Relocation Project
October 29, 2018 UPDATE – Southern Constructors and their
subcontractors will implement intermittent daily lane closures as needed this
week for saw-cutting asphalt and other pre-construction activities for the
wastewater system upgrades near the west ramp on W. Jackson Avenue (see
attached map). Wastewater system construction is expected to start in
approximately two weeks. This section of W. Jackson Avenue will reopen to
normal traffic flows when crews are not working. At least one lane of traffic
will remain open to maintain traffic flow. Access to parking areas and area businesses
will be maintained.
Friday, October 26, 2018
Depot Avenue Water Main Project
October
26, 2018 UPDATE –
Contractor Garney Construction completed installation of the
36-inch water main on the section of Patton Street between E. Jackson Avenue
and Willow Avenue. This section of Patton Street will remain closed through
November 9 for paving and restoration work. Once paving and restoration are
complete on Patton Street, crews will move to Willow Avenue to continue
installation of the 36-inch water main. The Patton Street intersection and
approximately 300 feet of Willow Avenue east of the intersection will be closed
starting October 30 through early November. A second Garney Construction crew
completed installation and testing of a new 8-inch water main along the section
of W. Depot Avenue between N. Gay Street and Williams Street. Tie-ins are
scheduled in the area through October 31, followed by paving and restoration
through November 9.
This
section of W. Depot Avenue will remain closed as part of an ongoing non-KUB
development project in the area.
Sequoyah Hills Wastewater Project
October 26, 2018 UPDATE –
Weekly Update: Hurst Excavating completed
rehabilitation of the wastewater main and manholes on Noelton Drive between the
Kingston Pike intersection and Chippewa Circle this week. Paving and
restoration work requiring intermittent daily road closures will continue in
this area through November 2. Construction activities continue on Chippewa
Circle, and the work zone on Noelton Drive has been expanded down to Alta Vista
Way. Paving and restoration work requiring intermittent daily closures will
also continue on Hiawatha Drive and Chickasaw Drive next week.
Jackson Avenue Ramps Utility Relocation Project
October 26, 2018 UPDATE –
Contractor Southern Constructors and their subcontractors
completed testing and tie-ins on the domestic and fire protection water lines.
Water line connections on a hydrant at Jackson Terminal and an 8-inch line
going to Fire Alley are scheduled for Monday, October 29. Final natural gas
connections have been moved to next week, October 29-31, due to inclement
weather. Wastewater work requiring traffic closures on W. Jackson Avenue is
expected to begin in early November. Information on the scope and duration of
traffic closures will be communicated in advance, as details are finalized.
South Knox Natural Gas Project
October 26, 2018 UPDATE –
Pipeline:
Restoration work remains in one area between W. Marine Road and Henry Haynes.
All other restoration work has been completed.
Gate
Station: KUB contractor
Cenergy continued conduit installation and pipe testing this week. Next week,
crews will be coating and backfilling newly-installed pipe. Conduit and wiring
installation will also continue next week.
Friday, October 19, 2018
South Knox Natural Gas Project
October 19, 2018 UPDATE –
Pipeline:
Restoration work remains in one area between W. Marine Road and Henry Haynes.
All other restoration work has been completed.
Gate
Station: KUB contractor
Cenergy installed one control building onsite this week. Testing activities
slated for this past weekend have been rescheduled for this coming Sunday and
Wednesday evenings. This work will be isolated to the gate station construction
site with no impacts to customers. Installation of conduit and excavation for
station inlet and outlet piping will continue next week.
Jackson Avenue Ramps Utility Relocation Project
October 19, 2018 UPDATE – Contractor Southern Constructors has completed installation of the
natural gas and water mains. Tie-ins to the existing natural gas main are
scheduled for completion next week. Crews will also condemn the old natural gas
main in this area next week. Water main testing was completed successfully, and
tie-ins are ongoing. The alley on the north side of the ramps, adjacent to
Jackson Terminal remains closed, but access is maintained to businesses.
Wastewater work requiring traffic closures on W. Jackson Avenue is expected to
begin in early November. Information on the scope and duration of traffic
closures will be communicated in advance, as details are finalized.
Sequoyah Hills Wastewater Project
October
19, 2018 UPDATE – Hurst Excavating continued rehabilitation of the wastewater main
and manholes on Noelton Drive between the Kingston Pike intersection and
Chippewa Circle this week. In addition to continued work on Noelton Drive next
week, crews will expand the work zone to include all of Chippewa Circle. This
section of Noelton Drive and Chippewa Circle will remain closed to through
traffic daily from 7 a.m. – 5 p.m. through next Friday, October 26. Alternate
routes include Alta Vista Way and Scenic Drive. All lanes will reopen to normal
traffic flow outside of the listed work hours and on weekends. Access to
driveways will be maintained. Crews also continued construction in the off-road
easement between Shawnee Lane and Hiawatha Drive, and on Chickasaw Road this
week, and work will continue in those areas next week. Paving and restoration
work will also continue on Hiawatha Drive (between Noelton Drive and Towanda
Trail) and in the off-road easement between Hiawatha Drive and Alta Vista Way
next week.
Depot Avenue Water Main Project
October 19, 2018 UPDATE – The N. Gay Street at W.
Jackson Avenue intersection will be temporarily reopened to normal flow
starting at 5 p.m. Friday, October 19, through 7 a.m., Monday, October 22, to
accommodate increased traffic in the area for this weekend’s Tennessee vs.
Alabama game. The intersection and road closure on W. Jackson Avenue will
resume Monday and last through November 2 as testing, paving, and restoration
work is performed in this area. Garney Construction continued installation of the 36-inch
water main this week along the section of Patton Street between E. Jackson
Avenue and Willow Avenue. Work will continue in this area next week,
progressing towards the Willow Avenue intersection. Additional information will
be sent out regarding the scope and duration of work in this area prior to the
start of construction. A short section of E. Jackson Avenue, including the
Patton Street intersection, will remain closed until paving and restoration
work is completed next Tuesday, October 23 (weather permitting).
West Hills Natural Gas Project
October 19, 2018 UPDATE –
ZONE
4 – KUB and
East Tennessee Pipeline crews continued to replace the natural gas mains on
Dorchester Drive and Newcastle Drive this week. Work will continue on those
streets next week.
Zones
1-3 Right-of-Way Restoration – Per notices mailed by KUB to customers in early October, right of
way restoration, including re-seeding and placing straw, is underway in areas
where excavation occurred as part of the pipeline installation project.
Wednesday, October 17, 2018
Sequoyah Hills Wastewater Project
TRAFFIC ADVISORY
(West
Knoxville) Kingston Pike and Noelton Drive Lane, Road Closure [October 18] – KUB contract crews will implement the below traffic control
measures from 9 a.m. – 3 p.m. on Thursday, October 18, as work continues on the
wastewater collection system in the area:
· Both the
westbound and eastbound turn lanes of Kingston Pike at Noelton Drive CLOSED
(eastbound and westbound traffic will be maintained)
· Notelton
Drive between Kingston Pike and Shawnee Lane CLOSED
Eastbound and westbound Kingston Pike traffic
will be maintained while through traffic will not be maintained through the
intersection. Noelton Drive should be accessed via Mellen Avenue, Towanda
Trail, Hiwatha Drive, or Scenic Drive. Flaggers and signs will be on site to
assist with traffic control. Follow-up advisories will be issued as necessary.
Tuesday, October 16, 2018
Depot Avenue Water Main Project
TRAFFIC ADVISORY
(Old City) N. Gay Street, W. Depot Avenue Intersection Closure [October
17-26] – KUB contract
crews will close the intersection of N. Gay Street and W. Depot Avenue beginning
at 7 a.m. on Wednesday, October 17, through 5 p.m. Friday, October 26, as work
is performed on the water distribution system in the area. This closure will
remain in effect throughout the weekend. Flaggers and signs will be on site to
assist with traffic control. Alternate
routes include N. Broadway and N. Central Street. Follow-up advisories will be
issued as necessary.
Friday, October 12, 2018
West Hills Natural Gas Project
ZONE
4 – KUB and
East Tennessee Pipeline crews continued to replace the natural gas mains on
Dorchester Drive and Newcastle Drive this week. They will continue work on
those streets next week.
Depot Avenue Water Main Project
October 12, 2018 UPDATE –
Garney Construction crews completed
installation of the 36-inch water main this week along E. Jackson Avenue, and
began installation on the section of Patton Street between E. Jackson Avenue
and Willow Avenue. The E. Jackson Avenue at Patton Street intersection will be
re-opened for area events this weekend, including Oktoberfest in the Old City
on Saturday, October 13, and the Subway Race Against Cancer on Sunday, October
14. The intersection will re-close the week of October 15 for paving and
restoration work. Patton Street will also be closed between E. Jackson Avenue
and Willow Avenue all of next week as the 36-inch water main is installed in
this area. Saw-cutting and construction prep work began on the section of W.
Depot Avenue between N. Gay Street and Williams Street this week. Crews will
install an 8-inch water main in this area starting next week. This section of
W. Depot Avenue is already closed to traffic as part of an ongoing development
project in the area; however, Garney crews will need to expand the closure zone
to include the N. Gay Street at W. Jackson Avenue intersection tentatively set
for October 17-24. Additional information will be sent out early next week as
the schedule for work in this area is finalized.
Sequoyah Hills Wastewater Project
October 12, 2018 UPDATE –
Hurst Excavating began
installation of the new wastewater main on Noelton Drive between the Kingston
Pike intersection and Chippewa Circle this week. This section of Noelton Drive
will remain closed to through traffic daily from 7 a.m. – 5 p.m. through next
Friday, October 19. Alternate routes include Alta Vista Way and Scenic Drive.
All lanes will reopen to normal traffic flow outside of the listed work hours
and on weekends. Access to driveways will be maintained. Crews also continued
construction in the off-road easement between Shawnee Lane and Hiawatha Drive,
and on Chickasaw Road this week, and work will continue in those areas next
week. Paving and restoration work will also continue on Hiawatha Drive (between
Noelton Drive and Towanda Trail) and in the off-road easement between Hiawatha
Drive and Alta Vista Way next week.
Jackson Avenue Ramps Utility Relocation Project
October 12, 2018 UPDATE –
Contractor Southern Constructors completed installation and tested
the new natural gas main. Next week, crews will tie-over customer service lines
to the new main and repair asphalt cuts. Temporary shifting lane closures will
be needed at the W. Jackson Avenue and State Street intersection while this
work is completed on October 17-19. At least one lane of traffic will remain
open at all times Crew will also continue installation and testing on the new
water main next week. Access to the Jackson Avenue parking lot and area businesses
will be maintained at all times.
South Knox Natural Gas Project
October
12, 2018 UPDATE –
Pipeline:
Restoration work will continue in the area between W. Marine Road and Henry Haynes
Road next week.
Gate
Station: KUB contractor
Cenergy continued wiring and piping installation this week. A crew will be
onsite this Sunday, October 14, to perform testing on a portion of
newly-installed pipe. Crews also plan to work overnight on Wednesday, October
17, to continue testing sections of new pipe. A generator will be used as part
of this work, but no large equipment will be used.
Friday, October 5, 2018
South Knox Natural Gas Project
October 5, 2018 UPDATE – Pipeline:
Restoration work will continue in the area between W. Marine Road and Henry
Haynes Road next week. Gate
Station: KUB contractor
Cenergy continued wiring and piping installation this week. The newly-installed
piping will be ready for testing next week.
Overall Project
Update: Pipeline
construction is complete, with a total of 4,600-feet of natural gas pipeline
installed between Chapman Highway and Tipton Station Road. Work continues on
the new South Knox Gate Station located at 409 Tipton Station Road. The gate station
is approximately 45-percent complete as of early October.
Construction
continues to progress on the new KUB South Knox Natural Gas Gate Station
located at 409 Tipton Station Road.
Sequoyah Hills Wastewater Project
October 5, 2018 UPDATE – Hurst Excavating crews are
scheduled to begin installation of the new wastewater main on Noelton Drive,
between the Kingston Pike intersection and Chippewa Circle, starting Monday,
October 10. This section of Noelton Drive will be closed to through traffic
daily from 7 a.m. – 5 p.m. Alternate routes include Alta Vista Way and Scenic
Drive. All lanes will reopen to normal traffic flow outside of the listed work
hours and on weekends. Access to driveways will be maintained. Crews will also
continue construction in the off-road easement between Shawnee Lane and
Hiawatha Drive, and on Chickasaw Road next week. Paving and restoration work will
also continue on Hiawatha Drive (between Noelton Drive and Towanda Trail) and
in the off-road easement between Hiawatha Drive and Alta Vista Way next
week.
Overall Project Update: Construction in the Phase 1
area is approximately 75 percent complete. To date, approximately 21,000 linear
feet of wastewater mains have been installed, and 180 customer service laterals
have been reconnected.
Phase 1 streets where work has been completed include:
·
Scenic Drive
·
Southgate Road
·
Calumet Drive
·
Wilani Road
·
Taliluna Ave*
·
Keowee Ave *
·
Sequoyah Ave*
*Phase 1 work complete;
however, these streets also have remaining work on them
in Phase
2.
Phase 1 streets where work is ongoing or remains:
·
Noelton Drive (construction begins
October 8)
·
Kingston Pike
·
Kingston Park Drive
·
Arrowhead Trail
·
Sylvan Lane
·
Blows Ferry (approximately one week
of clean-up remaining)
·
Alta Vista Way (approximately one
week of clean-up remaining)
·
Mellen Avenue (one manhole to
replace)
·
Valencia Road
·
Chickasaw Road (construction
underway)
·
Hiawatha Drive (clean-up restoration
remaining)
·
Dogwood Lane
·
Chippewa Circle
·
Towanda Trail
(Sequoyah Hills) Sequoyah
Hills Area Road Closures [October 8-12] – KUB contract crews will implement the below
road closures as needed daily,
Monday-Friday, from 7 a.m. – 5 p.m., October 8-12, as
work continues on the wastewater collection system in the area:
- Hiawatha Drive between Noelton Drive and Towanda Trail
- Arrowhead Trail between Dogwood Lane and Alta Vista Way
- Noelton Drive between Kingston Pike and Chippewa Circle
Jackson Avenue Ramps Utility Relocation Project
October 5,
2018 UPDATE – Contractor
Southern Constructors continued installation of the 12-inch water main, with
crews working beneath the Gay Street overpass and progressing east. Natural gas
main installation crews also started working on the eastern extents of the
project this week. Water work will continue in the area next week. Next week,
natural gas construction crews will reduce W. Jackson Avenue to one alternating
lane of traffic near the State Street intersection daily from 7 a.m. – 4 p.m.,
October 8-10, as tie-in connections are made. Flaggers and signage will be in
place to assist with maintaining traffic flow. This section of W. Jackson
Avenue will re-open to normal traffic flow outside of listed work hours. Access
to the Jackson Avenue parking lot and area businesses will be maintained at all
times.
Overall
Project Update: The overall project is approximately 30-percent complete,
including 283-feet of 12-inch water main and 287-feet of 4-inch natural gas
main. Wastewater system work will begin after water main is installed.
(Old City) W. Jackson Avenue Lane Closure [October 8-10] – KUB contract crews will reduce a short
section of W. Jackson Avenue between N. Central Street and State Street to one
alternating lane of traffic from 7 a.m. – 4 p.m. daily, starting Monday,
October 8, through Wednesday, October 10, as work is performed on the natural
gas distribution systems in the area. The westbound lane will be closed while
the eastbound lane remains open and is used to alternate traffic through the
work zone. Flaggers and signs will be on site to assist with traffic control. Follow-up advisories will be issued as
necessary.
Depot Avenue Water Main Project
October 5, 2018 UPDATE – Garney Construction crews continued the
installation of the 36-inch water main this week along E. Jackson Avenue,
progressing toward Patton Street. Pipe installation and paving work will
continue along E. Jackson Avenue as shown on the accompanying map through
October 17. Beginning Monday, October 8, Garney will implement a work zone on Patton
Street to continue installation of the 36-inch main. Paving and
restoration work was completed on E. Depot Avenue and Morgan Street as of
October 5, and both roads have been re-opened to normal traffic flow. E.
Jackson Avenue has also been re-opened to traffic to allow access to the Old
City parking area beneath the James White Parkway/Hall of Fame Drive overpasses
from the west (Morgan Street). In addition to the work zones mentioned above,
Garney Construction is scheduled to begin installation of a short section of
8-inch water main on W. Depot Avenue between N. Gay Street and Williams Street
on Wednesday, October 10. This section of W. Depot Avenue is already closed to
traffic as part of an ongoing development project in the area.
Overall
Project Update: The
Depot Avenue Area Water Main Installation Project is approximately 93 percent
complete overall. Pipe totals installed to date include 6,670 linear feet of
36-inch water transmission main, 2,415 linear feet of 8- to 16-inch water
distribution main, three fire hydrants, and 23 service line reconnections.
West Hills Natural Gas Project
October 5,
2018 UPDATE – ZONE
4 – KUB and
East Tennessee Pipeline crews continued to replace the natural gas mains on
Dorchester Drive and Newcastle Drive this week. They will continue work on
those streets next week.
Overall
Project Update: Zone 1 –
Complete as of April 2018 with 7,200-feet of main replaced and 64 services;
Zone 2 – Complete as of September 2018 with 9,100-feet of main replaced and 70
services; Zone 3 – Complete as of July 2018 with 11,100-feet of main replaced
and 110 services; Zone 4 – 90 percent complete as of early October with
9,100-feet of main replaced and 60 of 103 services completed (work remains on
Dorchester Drive and Newcastle Drive).