Sequoyah Hills Wastewater Project


October 12, 2018 UPDATE –

Hurst Excavating began installation of the new wastewater main on Noelton Drive between the Kingston Pike intersection and Chippewa Circle this week. This section of Noelton Drive will remain closed to through traffic daily from 7 a.m. – 5 p.m. through next Friday, October 19. Alternate routes include Alta Vista Way and Scenic Drive. All lanes will reopen to normal traffic flow outside of the listed work hours and on weekends. Access to driveways will be maintained. Crews also continued construction in the off-road easement between Shawnee Lane and Hiawatha Drive, and on Chickasaw Road this week, and work will continue in those areas next week. Paving and restoration work will also continue on Hiawatha Drive (between Noelton Drive and Towanda Trail) and in the off-road easement between Hiawatha Drive and Alta Vista Way next week. 