Friday, October 5, 2018

Sequoyah Hills Wastewater Project

October 5, 2018 UPDATE – Hurst Excavating crews are scheduled to begin installation of the new wastewater main on Noelton Drive, between the Kingston Pike intersection and Chippewa Circle, starting Monday, October 10. This section of Noelton Drive will be closed to through traffic daily from 7 a.m. – 5 p.m. Alternate routes include Alta Vista Way and Scenic Drive. All lanes will reopen to normal traffic flow outside of the listed work hours and on weekends. Access to driveways will be maintained. Crews will also continue construction in the off-road easement between Shawnee Lane and Hiawatha Drive, and on Chickasaw Road next week. Paving and restoration work will also continue on Hiawatha Drive (between Noelton Drive and Towanda Trail) and in the off-road easement between Hiawatha Drive and Alta Vista Way next week. 

Overall Project Update: Construction in the Phase 1 area is approximately 75 percent complete. To date, approximately 21,000 linear feet of wastewater mains have been installed, and 180 customer service laterals have been reconnected.
Phase 1 streets where work has been completed include:


·         Scenic Drive
·         Southgate Road
·         Calumet Drive
·         Wilani Road
·         Taliluna Ave*
·         Keowee Ave *
·         Sequoyah Ave*

*Phase 1 work complete; however, these streets also have remaining work on them in          Phase 2. 

Phase 1 streets where work is ongoing or remains:


·         Noelton Drive (construction begins October 8)
·         Kingston Pike
·         Kingston Park Drive
·         Arrowhead Trail
·         Sylvan Lane
·         Blows Ferry (approximately one week of clean-up remaining)
·         Alta Vista Way (approximately one week of clean-up remaining)
·         Mellen Avenue (one manhole to replace)
·         Valencia Road
·         Chickasaw Road (construction underway)
·         Hiawatha Drive (clean-up restoration remaining)
·         Dogwood Lane
·         Chippewa Circle
·         Towanda Trail

(Sequoyah Hills) Sequoyah Hills Area Road Closures [October 8-12] – KUB contract crews will implement the below road closures as needed daily, Monday-Friday, from 7 a.m. – 5 p.m., October 8-12, as work continues on the wastewater collection system in the area:
  • Hiawatha Drive between Noelton Drive and Towanda Trail
  • Arrowhead Trail between Dogwood Lane and Alta Vista Way
  • Noelton Drive between Kingston Pike and Chippewa Circle
Additionally, Chickasaw Road between Cherokee Boulevard and Navaho Road will be closed continuously through Friday, October 12, due to extensive excavation. Access to area homes will be maintained, and flaggers and signs will be on site to assist with traffic control. Unless otherwise indicated, roadways will be re-opened outside of work hours. Follow-up advisories will be issued as necessary.  

No comments:

Post a Comment