Overall Project Update: Construction in the Phase 1
area is approximately 75 percent complete. To date, approximately 21,000 linear
feet of wastewater mains have been installed, and 180 customer service laterals
have been reconnected.
Phase 1 streets where work has been completed include:
·
Scenic Drive
·
Southgate Road
·
Calumet Drive
·
Wilani Road
·
Taliluna Ave*
·
Keowee Ave *
·
Sequoyah Ave*
*Phase 1 work complete;
however, these streets also have remaining work on them
in Phase
2.
Phase 1 streets where work is ongoing or remains:
·
Noelton Drive (construction begins
October 8)
·
Kingston Pike
·
Kingston Park Drive
·
Arrowhead Trail
·
Sylvan Lane
·
Blows Ferry (approximately one week
of clean-up remaining)
·
Alta Vista Way (approximately one
week of clean-up remaining)
·
Mellen Avenue (one manhole to
replace)
·
Valencia Road
·
Chickasaw Road (construction
underway)
·
Hiawatha Drive (clean-up restoration
remaining)
·
Dogwood Lane
·
Chippewa Circle
·
Towanda Trail
(Sequoyah Hills) Sequoyah
Hills Area Road Closures [October 8-12] – KUB contract crews will implement the below
road closures as needed daily,
Monday-Friday, from 7 a.m. – 5 p.m., October 8-12, as
work continues on the wastewater collection system in the area:
- Hiawatha Drive between Noelton Drive and Towanda Trail
- Arrowhead Trail between Dogwood Lane and Alta Vista Way
- Noelton Drive between Kingston Pike and Chippewa Circle